<?xml version="1.0" encoding="UTF-8"?><project name="20260316_Zeitplan Nacke Logistik" company="" webLink="http://" view-date="2025-12-01" view-index="0" gantt-divider-location="417" resource-divider-location="300" version="3.3.3300" locale="de_DE">
|
||||
<description/>
|
||||
<view zooming-state="default:10" id="gantt-chart">
|
||||
<field id="tpd6" name="Dauer" width="52" order="0"/>
|
||||
<field id="tpd3" name="Vorgang" width="208" order="1"/>
|
||||
<field id="tpd4" name="Anfang" width="78" order="2"/>
|
||||
<field id="tpd5" name="Ende" width="78" order="3"/>
|
||||
<field id="tpd15" name="Notizen" width="20" order="4"/>
|
||||
<option id="filter.completedTasks" value="false"/>
|
||||
<option id="filter.dueTodayTasks" value="false"/>
|
||||
<option id="filter.overdueTasks" value="false"/>
|
||||
<option id="filter.inProgressTodayTasks" value="false"/>
|
||||
<option id="color.recent"><![CDATA[#66ffff #66ff66 #ff33ff #00ff66 #9999ff #ff9999 #660066 #0033ff #00ffff]]></option>
|
||||
</view>
|
||||
<view id="resource-table">
|
||||
<field id="0" name="Ressource" width="210" order="0"/>
|
||||
<field id="1" name="Rolle" width="86" order="1"/>
|
||||
</view>
|
||||
<!-- -->
|
||||
<calendars>
|
||||
<day-types>
|
||||
<day-type id="0"/>
|
||||
<day-type id="1"/>
|
||||
<default-week id="1" name="default" sun="1" mon="0" tue="0" wed="0" thu="0" fri="0" sat="1"/>
|
||||
<only-show-weekends value="false"/>
|
||||
<overriden-day-types/>
|
||||
<days/>
|
||||
</day-types>
|
||||
</calendars>
|
||||
<tasks empty-milestones="true">
|
||||
<taskproperties>
|
||||
<taskproperty id="tpd0" name="type" type="default" valuetype="icon"/>
|
||||
<taskproperty id="tpd1" name="priority" type="default" valuetype="icon"/>
|
||||
<taskproperty id="tpd2" name="info" type="default" valuetype="icon"/>
|
||||
<taskproperty id="tpd3" name="name" type="default" valuetype="text"/>
|
||||
<taskproperty id="tpd4" name="begindate" type="default" valuetype="date"/>
|
||||
<taskproperty id="tpd5" name="enddate" type="default" valuetype="date"/>
|
||||
<taskproperty id="tpd6" name="duration" type="default" valuetype="int"/>
|
||||
<taskproperty id="tpd7" name="completion" type="default" valuetype="int"/>
|
||||
<taskproperty id="tpd8" name="coordinator" type="default" valuetype="text"/>
|
||||
<taskproperty id="tpd9" name="predecessorsr" type="default" valuetype="text"/>
|
||||
</taskproperties>
|
||||
<task id="0" uid="b181596bcfbd443181b7d40c873bba24" name="Bestellung/ Anzahlung" meeting="false" start="2025-12-16" duration="1" complete="0" expand="true"/>
|
||||
<task id="2" uid="6d85c340e56b419a9e6ca32c248f3ee7" name="Freigabe Layout" meeting="false" start="2026-01-29" duration="40" complete="0" thirdDate="2026-01-29" thirdDate-constraint="0" expand="true">
|
||||
<depend id="1" type="2" difference="0" hardness="Strong"/>
|
||||
<depend id="3" type="2" difference="0" hardness="Strong"/>
|
||||
<depend id="4" type="2" difference="0" hardness="Strong"/>
|
||||
</task>
|
||||
<task id="1" uid="824f73eda79949e19338a5fc8bc2316c" name="Pflichtenheft erstellen" meeting="false" start="2026-03-26" duration="33" complete="0" thirdDate="2026-01-13" thirdDate-constraint="0" expand="true"/>
|
||||
<task id="3" uid="6b0237d7fbf84b5cb3d2dd1f154667bf" name="Bestellung Fahrstrecken" meeting="false" start="2026-03-26" duration="6" complete="0" thirdDate="2024-09-02" thirdDate-constraint="0" expand="true">
|
||||
<depend id="6" type="2" difference="0" hardness="Strong"/>
|
||||
</task>
|
||||
<task id="4" uid="63513b12062844859a3e34f3e3a38de4" name="Bestellung Gerüst" meeting="false" start="2026-03-26" duration="6" complete="0" thirdDate="2024-09-02" thirdDate-constraint="0" expand="true">
|
||||
<depend id="6" type="2" difference="0" hardness="Strong"/>
|
||||
</task>
|
||||
<task id="6" uid="a2044c416835451f947b50e6bbc33411" name="Beschaffung Produktion" meeting="false" start="2026-04-03" duration="66" complete="0" thirdDate="2024-09-02" thirdDate-constraint="0" expand="true">
|
||||
<depend id="7" type="2" difference="0" hardness="Strong"/>
|
||||
</task>
|
||||
<task id="7" uid="c5ac0b5423ed4cb3996b311a1f128a0c" name="Transport/ Anlieferung" meeting="false" start="2026-07-06" duration="1" complete="0" thirdDate="2024-09-02" thirdDate-constraint="0" expand="true">
|
||||
<depend id="8" type="2" difference="0" hardness="Strong"/>
|
||||
</task>
|
||||
<task id="8" uid="fb777d7a6cd24a6a8288f4a0a7a291ce" name="Montage Gerüst_Fördertechnik" meeting="false" start="2026-07-07" duration="69" complete="0" thirdDate="2026-03-16" thirdDate-constraint="0" expand="true">
|
||||
<depend id="11" type="2" difference="0" hardness="Strong"/>
|
||||
</task>
|
||||
<task id="9" uid="fce1b9e35d1348d5939b907c9f68a29f" name="Montage elektrisch" meeting="false" start="2026-09-24" duration="8" complete="0" thirdDate="2024-09-02" thirdDate-constraint="0" expand="true">
|
||||
<depend id="10" type="2" difference="0" hardness="Strong"/>
|
||||
</task>
|
||||
<task id="10" uid="b854e03228bb4adfa635db1a721682c9" name="Inbetriebnahme" meeting="false" start="2026-10-06" duration="5" complete="0" thirdDate="2024-09-02" thirdDate-constraint="0" expand="true">
|
||||
<depend id="11" type="2" difference="0" hardness="Strong"/>
|
||||
</task>
|
||||
<task id="11" uid="628d128e20c24643991643175c0f15cd" name="Puffer Restarbeiten" meeting="false" start="2026-10-13" duration="3" complete="0" thirdDate="2024-09-02" thirdDate-constraint="0" expand="true">
|
||||
<depend id="12" type="2" difference="0" hardness="Strong"/>
|
||||
</task>
|
||||
<task id="12" uid="c7acb9cbf40a4f14a689706376cd3f08" name="Abnahme" meeting="false" start="2026-10-16" duration="1" complete="0" thirdDate="2024-09-02" thirdDate-constraint="0" expand="true"/>
|
||||
</tasks>
|
||||
<resources/>
|
||||
<allocations/>
|
||||
<vacations/>
|
||||
<previous/>
|
||||
<roles roleset-name="Default"/>
|
||||
</project>
|
||||